Pebble Beach CSD Undergrounding of Overhead Utilities

Pebble Beach, CA

Project Description:

The Pebble Beach Community Services District maintains a fund to convert approximately ten miles of overhead utility lines throughout the Pebble Beach community to underground, to promote safety and improve reliability for their residents and visitors. The overall project has been divided into six phases, each roughly one to two miles long and administered under the PG&E Rule 20B Tariff. Two of the six phases have been completed to date, and construction of the third phase will start in the first quarter of 2021. Wallace Group prepared the Basis of Design Evaluation and continues to serve as the liaison between the utility companies and Pebble Beach CSD, facilitate design efforts, and promote client goals through planning, design, and construction.

Project Highlights:

Phase I

  • 1.5 miles
  • 11 residences converted from overhead to underground service
  • Duration: 3 years


Phase II

  • 2.2 Miles
  • Duration: 5 years (2014-2019)


Phase III

  • 2.2 miles
  • Design currently underway

Client

Pebble Beach Community Services District

Services Provided

Construction Management
Mechanical Engineering
Water Resources
Bg dark

Want to work with us?

Get in touch
Bg projects

Want to make our communities better?

4fd8b2af48b65b3cb139e52790fc452f Ec89c2fdfc0cff61185f173ae4bbd183 5d4514ab591831926b73d888cebb1565 2dda63642c8ee02fc03e6c1ee6ae7f5f